MARR M2480D COMPLETES PROJECT MILESTONE LIFT ON BLUESCOPE NO. 6 BLAST FURNACE RELINE PROJECT
Marr M2480D lifting the 170T, 54m-long downcomer at BlueScope No6BF Reline Project

MARR M2480D COMPLETES PROJECT MILESTONE LIFT ON BLUESCOPE NO. 6 BLAST FURNACE RELINE PROJECT

TRADE PRESS ANNOUNCEMENT
DECEMBER 2024

NEW SOUTH WALES, AUSTRALIA: The BlueScope No. 6 Blast Furnace (6BF) Reline Project has reached a major milestone with Marr Contracting’s M2480D Heavy Lift Luffing tower crane successfully removing the 6BF downcomer in a carefully planned engineering feat at the Port Kembla Steelworks (PKSW).

The removal of the 170-tonne, 54-metre long downcomer was safely completed using the 330-tonne capacity M2480D, with Marr’s 400-tonne Grove mobile crane used to assist with rotating the downcomber once it had be lowered to ground level.

Once removed and lowered to the ground by the M2480D, the downcomer was horizontally rotated and placed on Marr-supplied supports and reconfigured to be transported for refurbishment and replacement.

Engineered and planned by the BlueScope Reline Project team in collaboration with Marr, the innovative heavy lifting solution provided a less complex and safer alternative to using a traditional heavy lift crawler approach.

With previous experience removing similar sections of plant on a similarly congested worksite during the Blast Furnace No.5 Reline Project, BlueScope’s team knew that using a large crawler crane and superlift combination would present numerous challenges due to the location of the project and the restricted space available on the site.

According to PKSW Project Director, Justin Reed, “Marr’s team have challenged our traditional thinking by enabling large sections of equipment that were previously maintained in situ to be lifted to ground for repairs or replacement.”

“The capability and capacity of the M2480D is a true game-changer for our project. At vertical industrial sites like a Blast Furnace we have always wished there was a ‘sky-hook’ that could deliver a lift at any point on the plant, and now we have a solution with significant lifting capacity,” Mr Reed said.

With safety and minimising disruption to production at PKSW a priority, Marr’s solution is also helping to mitigate risk to critical path by providing BlueScope with an instant cranage solution for a large volume of smaller lifts at site during the relining process.

Installed on a specifically-design 7.5 x 7.5m piled foundation, the M2480D provides the heavy lifting capacity required with the additional benefits of a small footprint and long reach across the project.

“By engaging us early in the planning stages, BlueScope’s team unlocked the possibility to develop a simple solution that helped to reduce complexity and secure the tight construction program.” said Marr’s Managing Director, Simon Marr.

The refurbished downcomer will be reinstalled in another major lifting operation using Marr’s M2480D in mid-2025.

BlueScope anticipates that the 6BF will be recommissioned in mid-2026.

DOWNLOAD IMAGES HERE

FOR MORE INFORMATION CONTACT:

Simon White
Liz Male Consulting
e: simonw@lizmale.co.uk
t: +44 (0)7935 703293

NOTE TO EDITORS:

ABOUT MARR CONTRACTING

Marr Contracting are world leaders in the design and delivery of heavy lift luffing tower cranes and heavy lifting services. With almost 100 years’ experience working on large-scale construction projects in Australia and around the world, their expertise spans the large-scale construction, mining, oil and gas, power, nuclear, major transport infrastructure, technology and marine sectors. Not just a crew and cranes for hire, they’re big thinkers and problem solvers who love a challenge with a string of ‘world firsts’ to their name – including the world’s largest capacity tower crane, the Marr 2480D Heavy Lift Luffing (HLL) crane. www.marr.com.au

ABOUT THE BLUESCOPE NO.6 BLAST FURNACE RELINE PROJECT

In August 2023, BlueScope announced approval of its plans to reline and upgrade the previously dormant No.6 Blast Furnace (6BF) at the Port Kembla Steelworks (PKSW). The project will play an important role in securing the Illawarra region’s steelmaking capacity beyond 2026 when the existing No. 5 blast furnace (5BF) completes its current production campaign.

One of only two major steelmaking plants in Australia, PKSW employs approximately 3,500 people and indirectly supports an additional 5,500 jobs in the Illawarra. The AU$1.15 billion project will include the furnace reline, repair and upgrade of ancillary plant equipment  with over AU$100 million of environmental improvement upgrades that will enable the plant to maintain production while at the same time investing in lower emissions steelmaking technologies as they emerge to ensure the future economic benefits of steelmaking for Australia. BlueScope anticipates that the 6BF will be recommissioned in mid-2026. https://www.bluescope.com/illawarra/environmental-responsibility/blast-furnace-reline

 

SHARE

Downside arrow

Related articles

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. And if the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

Marr Crane Silhouette

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.