1915ÇANAKKALE BRIDGE

1915ÇANAKKALE BRIDGE

A game changing solution for the world’s longest span suspension bridge.

SHARE

PROJECT OVERVIEW

Connecting the towns of Gelibolu (Gallipoli) on the European side of Turkey with Lapseki on the Asian side, Turkey’s 1915Çanakkale Bridge will be the longest span suspension bridge in the world. At a total length of 4.6kms with a central span of more than 2kms supported by 318m-high bridge towers, the engineering feats to construct the bridge are staggering – and so were the heavy lifting requirements.

1915ÇANAKKALE BRIDGE Crane - MARR Project
Client
DL E&C–LIMAK–SK ECOPLANT–YAPI MERKEZI JOINT VENTURE (DLSY JV)
Project
1915ÇANAKKALE BRIDGE
Location
TURKEY
Sector
MAJOR INFRASTRUCTURE
Date
2019 – 2021
Cranes

2 x M2480D

THE CHALLENGE

Our challenge was to develop a heavy lifting solution for the construction of the bridge towers that would decrease the construction program and associated risk, reduce cost and increase safety – while working 24/7 over water in a high wind area and an earthquake zone in the middle of the COVID-19 pandemic.

OUR SOLUTION

Working with the DLSY JV, we developed a solution using two of our M2480Ds that allowed large, modularised sections of the bridge towers to be fabricated in a controlled environment offsite before being delivered to the worksite by barge for installation instead of lifting smaller components and welding on-site.

Downside arrow
THE RESULT

The unparalleled lifting capacity of our M2480Ds was a game changer for the project, with two ‘world firsts’ during construction of the bridge towers. By modularising the structure into larger, heavier sections our solution reduced the number of lifts and the overall construction schedule, with less site-based activities and a higher level of on-site safety. On 18 March 2022, the 1915Çanakkale Bridge opened more than 12 months ahead of schedule.

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

When the DL E&C–Limak–SK ecoplant–Yapi Merkezi Joint Venture (DLSY JV) won the contract to construct the 1915Çanakkale Bridge, they had a clear idea about how they wanted to build the project, but they needed a craneage partner who could think outside the box to bring that vision to life.

Through working directly and collaboratively with DLSY JV’s project team on the front-end engineering design, Marr’s team of engineers was able to develop a non-traditional craneage methodology that met all the project requirements and allowed DLSY JV to construct the bridge in the way they wanted. “Getting us involved early in the design stage was key to the success of this project,” said Marr’s Managing Director, Simon Marr.

APRIL – AUGUST 2019

After working with DLSY JV to develop the craneage methodology for the project, two specially designed 330-tonne capacity M2480D Heavy Lift Luffing (HLL) cranes were shipped from Australia to Turkey, via Singapore. In a combined global effort with our engineers from Australia, the UK and Middle East working together, we fabricated specialised equipment for the project in our Middle Eastern fabrication facility.

Our first milestone on the project was to assemble both cranes on purpose-built quayside foundations. After building the 300 tonne grillages, the next job was to lift them from the quayside and install them at the bridge work front.

NOVEMBER 2019

Using the 2,200-tonne capacity Taklift 4 floating heavy barge crane, the cranes – each weighing 600 tonnes – were lifted from the quayside and transported to the worksites a kilometre off-shore on the Çanakkale Strait (the Dardenelles). It was the first of two world-first engineering feats on the project.

Using two of our Marr2480D heavy lift luffing tower cranes – each with a lifting capacity of 330 tonnes – our solution allowed large, modularised sections of the bridge towers to be fabricated in a controlled environment offsite before being delivered to the worksite for installation. This helped to de-risk the project by taking the fabrication and associated construction tolerances off critical path.

JUNE 2020

After climbing the cranes to their final height of 328 metres, the next major milestone was the installation of the upper cross beam (UCB). With the M2480D positioned 328 metres above the water, it took approximately 30 minutes (and a lot of planning) to lift the 155-tonne section into position – creating a new world record for the heaviest lift at height.

JULY-NOVEMBER 2020

By November 2020, DLSY JV had completed construction of the bridge towers ahead of schedule. Working at 24/7 availability, both M2480Ds worked at an average utilisation rate of 20 hours per day to complete:

8 x 160-tonne lifts
36 x 150-tonne+ lifts
208 x 100-tonne+ lifts

After successfully completing the construction of the bridge towers, the M2480D HLLs were climbed down the completed bridge towers and safely recovered.

MARCH 2022

On 18 March 2022, the 1915Çanakkale Bridge was officially opened more than 12 months ahead of schedule in a ceremony attended by Turkish President Recep Tayyip Erdoğan.

“Marr’s team have a reputation for technical competence and innovative thinking in developing strategies for heavy lifting projects of this scale, but what has impressed us most is their collaborative approach to finding a solutions that suited our construction methodology and programme, and then delivering it,” said DLSY JV Deputy Project Manager, Mr Alper Alemdarouglu.

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.