HINKLEY POINT C TUNNELLING & MARINE PROJECT

HINKLEY POINT C TUNNELLING & MARINE PROJECT

A heavy lifting solution for the UK’s biggest construction project

SHARE

PROJECT OVERVIEW

Hinkley Point C nuclear power station (HPC), being built by EDF, is one of Europe’s largest and most complex construction projects and the first new nuclear power station to be built in Britain in more than 30 years.

In 2017 Balfour Beatty were awarded the contract to deliver the tunnelling and marine works as one of three major packages of works the contractor is delivering on Hinkley Point C.

Around the same time, Balfour Beatty invited Marr to present the advantages of our heavy lift craneage solutions to members of their senior engineering and construction team and asked us to look at the lifting requirements they had planned for Hinkley Point C.

Hinkley Point C - Installing M2480D
Client
Balfour Beatty Civil Engineering
Project
Hinkley Point C Tunnelling & Marine Project
Location
Bridgewater, Somerset, United Kingdom
Sector
POWER GENERATION
Date
January 2019 – April 2021
Cranes

1 x M2480D

THE CHALLENGE

In what is one of the most complex marine engineering projects ever undertaken in the UK, Balfour Beatty’s scope of works was for the construction of the outtake and intake tunnels for the cooling water needed for the Nuclear Reactor Units 1 and 2. It involved installing the tunnel boring machines (TBMs) and associated tunnel segments and conveyer systems used for the removal of spoil during tunnel excavation works.

Balfour Beatty sought an alternative to the traditional approach of using  large crawler cranes and a yet-to-be designed gantry system. This would have required a lot of temporary works and double -handling of equipment for the tunnel construction and ring segments for the tunnel lining. Given the constrained site and topography, the original concept raised concerns around productivity.

OUR SOLUTION

Balfour Beatty’s open approach to early engagement with their supply chain, was ideally suited to Marr’s way of thinking about crane solutions on large infrastructure projects. We were able to look at the project with a fresh set of eyes and identified the opportunity to place one of our M2480D Heavy Lift Luffing (HLL) tower cranes in a location where it could offer a single solution for all the lifting requirements.

Downside arrow
THE RESULT

Balfour Beatty’s willingness to engage with us early in the planning stages for this project created the opportunity for us to design a craneage solution which:

  • lowered project risk by reducing the number of lifting and handling activities; and
  • enhanced productivity through the ability to pick and place segment bundles in one activity.
LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

Placing our M2480D on 72 metres of free-standing tower with a 102-metre radius boom and fly combination allowed Balfour Beatty to operate independently above the other cranes on site, reducing the potential for boom clash on the project.

With a capacity of 25 tonnes at 100-metre radius and a maximum lift capacity of 220 tonnes in this configuration, the solution provided the lifting capability required to pick materials and components from the tunnel segment storage area and lower them to the pit bottom in one lift. This removed the need for multiple gantry cranes and double handling and enabled the construction of the conveyor system.

The M2480D’s lift capacity and dual hook configuration also gave Balfour Beatty the ability to install the TBM with one crane and unlike a heavy lift crawler option, the M2480D required no Super Lift attachment to complete any of its lifts.

With the freestanding crane occupying significantly less area than a crawler, our solution helped to alleviate logistical complexity on the busy construction site.

Laydown areas were created because of the minimum radius capability of the M2480D – at 9 meters compared to circa 36 meters for a large crawler, with a footprint of approximately 16 square metres at its base. This also significantly improved laydown which would have been taken up to accommodate the travel and slew of a large crawler.

Collaborating on the basis of ‘cranes as a forethought, not an afterthought’ allowed us to position the right crane that met the overall needs of the project, as opposed to the traditional method of filling the site with multiple cranes.

The 100-metre-plus reach of the M2480D gave up to 570 per cent more coverage than would have been possible with an alternative cranage design.

The creation of extra laydown space for Balfour Beatty was substantial because of both the maximum and minimum radius of the crane’s capability. An estimated 17 per cent increase in storage and laydown space was achieved.

In a coastal location with a constant risk of high winds where safe operation in wind speeds above nine meters per second would have been largely unachievable for mobile and crawler cranes, the M2480D allowed operational lifts in conditions of up to 20 meters per second where the dynamics of the load allowed. This meant the availability of the crane was significantly higher than for other mobile and crawler options.

With just one crane in operation and only one crew needed to operate it, a considerable reduction in labour was available compared to the labour requirements for gantries and multiple crawlers because every time a hook is in operation, operators are required.

The installation of the TBM also presented Balfour Beatty with the challenge of how to lift and rotate a number of heavy components from transport to installation on the project, without using two separate cranes to rotate the loads – with the added complexity of working in a coastal location where high winds were a constant challenge. Compounding this complexity, a number of tower cranes were already working on the project for other contractors, creating the potential for boom-clash between tower cranes.

“Early engagement between Balfour Beatty and Marr enabled a safe and suitable foundation to be designed for this geotechnically complex location. The two stand out benefits of the crane were flexibility and dual hook ability. The boom length and very high lift capacity enabled tunnel operations to be flexible to the changing site configuration, allowing us to pick and place all plant, equipment and materials over a very large area of the site. Secondly, the dual hook lift ability enabled the crane to single-handedly pick and rotate heavy TBM components with ease, without the need for a second crane. A very impressive and versatile crane – it was great to have the opportunity to work with it!” said Patrick Brady, Temporary Works Manager, HPC Tunnels & Marine Contract, Balfour Beatty Major Projects.

SOCIAL IMPACT

Consistent with the commitments Balfour Beatty and Hinkley Point C have made to local employment and the development of a sustainable regional supply chain, Marr has contributed to the positive socio-economic benefits of the project through the sourcing of local labour and supplies, as well spending within the local economy.

LET'S TALK ABOUT HOW WE COULD ADD VALUE TO YOUR PROJECT

We work with our clients to find a craneage solution that works – no matter how big or complex the job is. If the right crane doesn’t already exist, we’ll build one to suit the needs of your project.

ABOUT US

We’re not just a crew and cranes for hire. We’re big thinkers and problem solvers who love a challenge. No problem is too big for us.

OUR PHILOSOPHY

We believe that the crane needs to suit the job, not the other way around. We don’t just hire cranes – we design craneage solutions.

OUR HERITAGE

We’re a third-generation family-owned and run business with a strong sense of tradition and loyalty engrained in what we do and how we work together.

OUR PEOPLE

We think of our team as ‘one big family’ of problem-solvers who love cranes and the challenge of working on complex, large-scale projects.

OUR APPROACH

We work with you to find an engineering solution that works. Delivering value through the unique combination of our knowledge, experience, proven service delivery and people.

OUR SERVICES

We’ve worked on some of the most complex and challenging large-scale construction projects across Australia and around the world.

OUR CRANES

We don’t just hire cranes – we design them. So, if the right crane for your job doesn’t already exist, we’ll build one.

OUR PROJECTS

With almost 100 years’ experience, we have a reputation for taking on projects that others can’t or won’t.

SAFETY, QUALITY & ENVIRONMENT

We take on the jobs that many others can’t or won’t – but we always put good business practices first.

SUSTAINABILITY

We take sustainability seriously. It’s inherent in our commitment to finding the best and most efficient solution to every job.

SOCIAL IMPACT

As problem-solvers who love a challenge, we are never shy of tackling the big issues.

DIVERSITY

We are committed to creating a diverse, inclusive and flexible workplace that reflects the clients and communities we work with.